• High-end build-out of office space
  • Required working out kinks with the new HVAC system and coordination with other contractors doing build-outs on 54 floors, as well as base building contractors finishing work
  • Implemented new furniture office front system with a zero-tolerance requirement, which meant that the soffits, walls and floors could not vary more than a sixteenth of an inch from the design dimension
  • Worked with the client and architect to value engineer the project and after eight iterations of the budget, Leopardo reduced the budget by 30 percent