- Renovation of an existing cytology lab
- Project completed in two phases in a fully-occupied lab operating 24/7
- Provided preconstruction and planning services for the phasing sequencing to keep the labs operational throughout construction
- Relocated the building’s existing plumbing and HVAC to accommodate the space’s new layouts
- Maintained close coordination with the owner and vendor for the installation of lab equipment and furniture
- Installation of continuous epoxy flooring including disruptive floor prep during normal operating hours
- Charcoal filters were used at all air returns and HEPA machines with charcoal filters were used to clean the air to control the odor of the epoxy floor