- 23,000-SF, multi-floor common area and food court renovation
- Reconfiguration of layout, custom furniture, storefronts, epoxy floor, millwork and new signage
- New first-floor security/reception desk and tenant directory wall
- Lighting upgrades on the second and fifth floors, including a large statement fixture hanging from the fifth floor atrium ceiling
- Upgrades to the public restrooms, including all new finishes, lighting, toilet partitions and new plumbing fixtures
- Installation of a verdant feature wall with a faux vertical garden
- Work was completed overnight to avoid disruption to the stations more than 40,000 daily commuters
- Steps were taken to maintain daily operations during construction, including the use of quick-setting materials to lay new flooring so it would be ready for foot traffic by morning